PARTY-A : TRUST/SOCIETY
PARTY-B: CONSTRUCTION FIRM
ORDER OF EVENTS IS AS BELOW.
The Trust/ Society elects its president every year.
The president for the year 2014-15 awarded the construction contract to PARTY-B.
PARTY-A signs a construction agreement with Party-B.
There is an ongoing conflict between the previous management committee and the new management committee of the year 2014-15.
The previous management committee highjacks the TRUST by passing a resolution (after calling a Extraordinary General Body Meeting of all members) that the PRESIDENT (who awarded the construction contract) and the management committee of the year 2014-15 have to be removed. The President was not informed about the Extraordinary General Body Meeting. The current Presidents terms is until Jan 2015.
In the Extraordinary General Body Meeting only 50 out of 2000 members were present.
The previous management committee removes the current management committee forcefully.
The Old Management Committee again takes over the trust.
The Old Management Committee which is now the new Management Committee now wants to cancel all contracts awarded by the PRESIDENT (who awarded the construction contract)
************************************************************************************************
Questions:
1) How can the agreement be saved and the construction work be continued.
2) What are the legal implications related to such situations.
Thanks