Hello,
I purchased an apartment in an under construction project in Thane, Maharashtra in January 2014.
I also completed the registration formalities for the said property with a possession date of 31st Dec 2017 with a 6 month grace period.
The builder has given a date of Dec 2019 in RERA at the time of RERA registration.
I am yet to get possession of the apartment and would like to know does the date in the registered date take precedence over the date mentioned in RERA while registering the project?
Appreciate any input.
Regards,
Aniket