hi
i have a flat in township of approximate 800 flats. my flat was in last phase of the township and got possession on the same in 2012.
New flats including my flat got emerged with the existing co-cooperative housing society.
We been chasing after society since one year to help in getting completion certificate / Occpuation certifcate from Builder.... managing committee of society is also chasing after the builder for the same .....but not able to get the same.
my question is
1) can we all flat owners approach the PMC for the same. we can help in this case???
2) can we go straight to consumer forum to file case against the builder.
Please share if you have good alternative for the same.
Regards
Amu