Dear Sir,
Need your valuable advice before taking any action against builder who is delaying handover of the apartment.As per agreement the property should be given possession by last month itself.But when approached builder he is saying that there were raw materials such as sand steel was unavailable last year so the further delay will be there.But there was not that much demand for raw materials as he procured mostly before itself.Also in agreement we have a clause for delay in raw materials so he is using that to escape from accountability.
Very much annoyed by his response.As we have bought it through Loan . And also staying in a Rented house. So it becomes difficult to meet all the expenses. Need your suggestions/ actions against builder.Hereby attaching the conversation mail we had with builder.
![](https://ssl.gstatic.com/ui/v1/icons/mail/profile_mask2.png)
|
May 28 (4 days ago)
![]() |
![]() ![]() |
||
![](https://mail.google.com/mail/ca/images/cleardot.gif)
![](https://ssl.gstatic.com/ui/v1/icons/mail/profile_mask2.png)
|
May 29 (3 days ago)
![]() |
![]() ![]() |
||
|
Dear,
Ref : Sale Agreement dated : 25.05.2012
We are performing the construction activity in full swing. And are planning to complete the project at the earliest. The construction was delayed in between due to non availability of raw materials like sand,Steels & Bricks etc., from December 2012 onwards. We have clearly mentioned in the construction agreement that the delay in availability of raw materials may delay the completion(In Builders agreement Page No.4,Para No.2,Point No.15 clearly mentioned. Moreover we were forced to progress the construction of Flat No.C1F1 due to the delay on payments made by you., which has caused further delay.
Thanking You,
With Rgds,