Anantha (SQS)     09 August 2018

Claims by a contractor after the final payment

Dear Members,

The civil contractor during the performance of the contract submits the claims on its incremental cost impact in lieu of changes in minimum wages. It is an item rates contract. Can it be honoured ? If so he did not raises the claims within the stipulated time frame ( immediately as per the contract ) from the event of occurance of the changes in the law. Request the feedback and suggestions from the honourable members.

 

Thanks

Anantha



Learning

 1 Replies

Srinivasa Rao Yaramati (advocate)     09 August 2018

if it is an item rate contract and it you are not mentioned any wage increse in your writen agrement you need not to honour wage incriment 