LCI Learning

Share on Facebook

Share on Twitter

Share on LinkedIn

Share on Email

Share More

DILIP SHAH (Senior Counselor and Analyst for Redevelopment of Housing Societies)     20 August 2011

Delay in possession of flats in redevelopment of hsg. soc.

DELAY IN POSSESSION OF FLATS IN REDEVELOPMENT OF HOUSING SOCIETY

Builders and developers play vital role in redevelopment of housing societies. Currently, the redevelopment mania of residential properties is booming in full swing and one finds in Mumbai that compound wall of every third property of a society is covered with tins as number of small time builders and real estate companies has joined the battle in an effort to grab a share of this fast rewarding pastry.

There is also likelihood of delay in completion of such projects followed by numerous complaints from the buyers when flats are not delivered in tine as documented. What do developers do when apartments are not finished on time? Some pay back their clients as part of a penalty clause.

It is a long ending tussle between builders and home buyers that never seems to end delivering projects on time. There are umpteen cases where builders have taken extra time to finish projects while leaving home buyers to suffer fiscal setbacks.

Imagine a situation where you have booked a house in an apartment complex while paying hefty EMIs and also the rent for the temporary place that you currently occupy. Any delay in getting into your own house obviously means a financial loss.

To make ease for the home buyers and to remove rotten from the housing sector, Housing Department is planning to introduce new norms to control the realtors. It has made changes in the draft bill and increase the proposed fine from a maximum of Rs 10 lakh to Rs 1 crore, said Sachin Ahir, Minister of state for Housing.

According to the Ahir “whereas in the draft bill to control the housing sector Rs. 10L was the maximum fine, on the other side market experts believes that penalty amount is insufficient for the developers.” Due to the several complaints from buyers department has taken it seriously and made the norms to ease it. The new draft states the maximum penalty for an errant builder is Rs one crore.” This decision has been taken in recent past  in a meeting which has spearheaded by Ahir and attended by the Gautam Chatterjee, principal secretary housing, and other senior Housing Department officials.

As per the fresh reports final decision is yet to be taken to the draft which will be tabled in the state legislature for setting up of a Housing Regulatory Authority. 

However, the only change today is that builders now have a penalty clause in their agreements with buyers. But that is not mandatory yet. There have been cases earlier where people have contested builders in courts but in most cases that is a long prolonged battle which not many are willing to go through.

There are cases where people have complained about delayed possession of apartments but these are not highlighted because there are no effective machineries available to redress their grievances. However, the larger and top class developers have their image to protect and to fulfill their commitment they include a penalty clause in agreements.

There are numerous causes for delays such as late government approvals, getting the completion certificate after a long wait, raw material delays, cement and steel procurement, manpower delay to list a few. Getting local approvals is a harrowing task and the new Environmental Impact Assessment clearance that is now mandatory can even take up to nine months. At any point in time, there is a 50 to 60 per cent shortfall in unskilled manpower in the market. Civil contractors executing projects have so much on their plate that managing different projects is becoming more and more difficult.

According to industry watchers, most developers face project delays. About 85-90 per cent projects are delayed in some way or the other and that a lot of the delays are not in the developer’s control. The delays on account of various reasons do affect the overall budget of a developer, increases the construction and storage cost and hit the brand image and future of the company. Of course, it has a direct impact on end-users as well.

A project in which the buyer has given a minimal advance, the pressure on the developer is far less compared to heavy advance acceptances. The buyer’s capital is stuck and they cannot go anywhere. In such a situation, strict penalty clauses are imposed. This is one reason why clients rely on top class developers who are sure of their deliveries.

The realty industry experts say that in the last few years, developers have taken up 10 times more projects compared to what they have done in their total lifetime. Have they thought where the availability of the labor, brick, steel and cement is? How will they manage all this? However, there are well-known construction companies who are trying to get more advanced technology for construction to match their deliveries. However, the cost of adopting such technologies in India is still very high and not many developers are able to benefit from it.

The solution lays in the urban development ministries plans to create a regulator for the real estate sector. The regulator would promote best practices and consumer interest. Where there is a delay, the regulator will ensure that penalty is paid by the developer. The regulator will also be considered as an ombudsman between the buyers and developers.

The housing societies often get confused about choosing the best or right or so to say, one HONEST builder. There are many cases where the dreams of members of the housing society are crashed when the terms of Development Agreement and time schedule of completion of project is not maintained by such opportune builders of III tier.

There are types of voracious builders of III tire who have abandoned or have delayed the redevelopment projects due to paucity of inflow or diversion of funds from the assigned projects in order to acquire more and more projects beyond their financial means or are simply not capable to execute the projects due to lack of competency.  

Building a home is a major decision for the lifetime and one would not want to take chances. It is said that till you do not leave your society, you are the KING. The day on which you handover your property to the builder for redevelopment and leave your society, the builder is the KING.

With regard to the buying of flats/premises in projects other than redevelopment also, there is an upward trend for buying the property. The cut down in interest rate and easy registration process has attracted more property buyers to invest on their dream home.

Today real estate is one of thriving industries and demand for residential and commercial property is increasing day-by-day. There are number of builders and developers in city who offer or promise special features to attract prospective buyers. However, there are some builders or developers who delay the completion of project and the buyers suffer mentally and financially.

There are property buyers who say his/her flat’s possession has been delayed by six months or more. Even those of reputed builders get delayed unexpectedly. The properties buyers are the now considered consumers and finally have got a voice and a forum to air their grievances. Using consumer courts, buyers have been able to get back their money with interest or have been financially compensated besides allotment of flats by the sloppy builders.

In case of delay, the builder is liable to refund the amount paid with interest (for the period of delay) as there has been a breach of contract. A promoter, who constructs or intends to construct either commercial or residential building, shall specify in writing, the date by which possession of the flat is to be handed over.

In case of delay, as there has been a breach of contract, the builder would attract penalty under both Consumer Protection Act and the Maharashtra Ownership Flats Act. The builders are careless about compensation because there is no detailed written down Real Estate Regulator from the Government as yet, for rigorous punishment to such builders. A consumer doesn’t want to get into a legal tangle and just wants his flat in hand and the unscrupulous builders take advantage of this helplessness.

Many property aspirers buy an under-construction flat for the convenience of slab-wise payment and lower rates. But is it such a good idea? A Mumbai consumer says her flat's possession has already been delayed by six months. Like her, scores go through the harrowing wait for possession when housing projects-even those of reputed builders-get delayed unexpectedly. To add to their woes, consumers complain that builders rarely offer compensation, leave alone actually doing it out.

Now, consider the financial implications of delayed possession. A Mumbai consumer who was promised his flat in June 2007 says, "My agreement document clearly says that in case I intend to return the flat over delayed possession, the builder will refund the original amount with 9% interest from the day one he received the payment."

However, the flat purchaser calls this an impractical solution. "Prices have more than doubled since we booked the flat, so giving it up for just 9% interest does not make sense." Besides, he says, the interest rate on borrowed money has also seen a steep rise. During the unfortunate wait, buyers lose out in other ways too. One, if they don't own another property, they have to stay put in a rented place.

Two, if they have secured a home loan for the flat, its repayment schedule is treated as pre-EMI (equated monthly installment) till the buyer gets the property's possession. A buyer is entitled to tax rebate under sections 24 (b) and 80 (c) of the Income-Tax Act 1961, after securing possession of the property and thus commencement of EMI. Till then, he gets no tax relief on the pre-EMI.

Property buyer can present their own cases in consumer courts and do not need to engage a lawyer. The property buyer must file his complaint within two years of the dispute arising, after which it becomes outdated. A written complaint, can be filed before the District Consumer Forum for property value of up to Rupees twenty lakhs, State Commission for value up to Rupees one crore and the National Commission for value above Rupees one crore.

The builder problems can’t justify the delay. The default on the part of the builder would attract penalty under both Consumer Protection Act and the Maharashtra Ownership Flats Act, 1963. Often, the builders have an agreement clause that assures buyers a daily damage for the delayed possession. The buyers must ensure that his agreement for purchase of flat includes the clause compensation from the builder for delay in possession.

If such compensation clause for delay in possession of flat is included as penalty clause in the agreement for purchase of flat entered between the buyer and the builder i.e. monetary compensation for per day's/per month’s delay, buyer can be sure to get the compensation. The study of recent cases of delayed possession is re-produced below for the awareness of the flat/premises buyers:

BUILDERS CHEAT EARLY BUYERS, SAYS STATE COMMISSION

 

A landmark judgment recently delivered by a State Commission has ensured redress for a harassed Matunga couple. The Maharashtra State Consumer Disputes Redressal Commission directed Khar-based Monish Builders to pay Arti and Vikas Modi Rs 7.86 lakh as damages and hand over possession of the Chunabhatti flat they had bought in 2006.

 

The Consumer forum, while delivering the judgment, said that "When the purchasers complain, the builders show them provisions of the Maharashtra Ownership of Flats Act, 1963 and willingness to give full refund with interest at 9% from the date they received the money so that after using the flat buyer's money liberally for years, the builder can later sell the flat at much higher rate and pocket huge profit thereafter."

 

The Modis booked a 580 sq. ft flat in Mohan Mansion, Chunabhatti, for Rs 22.4 lakh. Over a period of time, the Modis paid the builder Rs 20.18 lakh. They were promised the possession of their flat before June 2007 but when the builder failed to deliver, Modis were forced to rent an apartment for five years.

 

The State Commission found the builders guilty of ‘Deficiency in Service’. In 2006, the Modis invested their life savings in a flat, and can't afford to buy one at the present rate, said the commission.

BUILDER FINED RS. 20 LAKH FOR DELAY: CONSUMER COURT

Mumbai: In an order that will cheer property buyers. As per the news item  appeared in "Times of India, dated 14 June' 2010, Mumbai edition, page 01" the Maharashtra State Consumer Commission recently directed a developer to shell out Rs. 20 lakh at the rate of Rs. 2,000 a day for a delay in giving possession of a shop premises to a purchaser.

The significance of the order passed by a three-member bench comprising president S B Mhase, S R Khanzode and D Dhamatkar—is that it is “among the first times’’ that “per day’’ damage, as was specified in the sale agreement, has been charged, according to lawyer Bindu Jain. The lawyer represented the aggrieved party, Dharshi Dedhia.

Often, builders have an agreement clause that assures buyers a daily damage for delayed possession, but few buyers, if any, invoke it, Jain said. The lawyer said the judgment comes as a boost to purchases of flats and other property across the state.

The commission said, “To issue notice for delivery of possession without an occupation certificate was an illegal act. We find that there is no ground to justify the delay.”

Dedhia possessed a shop and godown in Rajhans building in Thane as a tenant. The original landlord sold the premises to Padmavati Enterprises who decided to redevelop the property and agreed to give a shop of 366 sq ft to Dedhia at a subsidized rate. The agreement was made in June 2005 to hand over possession in October 2005, but the possession was given in June 2007 that too without an occupation certificate. As a result, Dedhia claimed damages for the delay at Rs. 2,000 per day as stipulated in the agreement.

Dedhia’s other grievance was that a water connection wasn’t given to him. He took up the matter with the Thane district consumer forum, which ordered the builder to pay him Rs. 20,000 as an additional compensation for the “mental agony and financial loss’’.

As already pointed out above, there have been innumerable decisions in Consumer Forums concerning builders and flat owners. These decisions have been rendered mostly on the ground of “deficiency in service”. Which expression has been defined in section 2(1) (g) and section 2(1) (o) of the Consumer Protection Act. In cases of delay in giving possession of the flats, the consumer forums have directed the refund of the amount deposited by the potential purchasers with the builder/housing board along with 18 per cent. In another case, besides issuing order for refund of the entire amount of Rs. 1,09,000/- deposited and payment of 18 per cent interest, the builder was also ordered to pay Rs. 1 lakh as further compensation.

BUILDER WAS DIRECTED TO PAY COMPENSATION FOR DELAYED FLAT DELIVERY

Mrs. Veena Khanna of New Delhi Vs M/s. Ansal Properties and Adharshila Towers, New Delhi: Before National Consumer Disputes Redressal Commission, New Delhi: Order dated 9th July 2007

Due to abnormal delay in handing over the possession of flat, the Complainant had demanded refund of the deposited amount with interest @ 18% which the Opposite party refused to pay. Complainant filed a petition before the State Commission, Delhi. By judgment and Order dt.06-12-2005, the State Commission directed the Opposite Party to refund the amount of Rs.15,00,000 with interest @ 13% p.a. from the date of deposit of the last installment till the date of payment of refund. In the alternative it also directed that if the Opposite Parties choose to handover the possession of the flat, the order of refund with interest will not come into operation.

Against the above Order of State Commission, the Complainant Mrs. Veena Khanna filed an Appeal in the National Consumer Dispute Redressal Commission praying that the Opposite Parties be directed to deliver the possession of the flat and also compensation for delay in delivery or adequate compensation should be awarded so that she can purchase a flat of the size.

It was argued that as the afore-quoted order passed by the State Commission gave preferable alternative to the Opposite Parties, and the builder took undue advantage of it and refunded the amount deposited by the complainant with interest, as directed, because of the rise in the prices of the immovable properties.

Opposite Parties took advantage only because an option was given to either refund the amount or to hand-over possession of the flat and no adequate compensation was awarded. The National Consumer Dispute Redressal Commission commented that if such contentions of refunding of the money with payment of minimal interest are accepted, the builders would earn millions of rupees by delaying the delivery of the possession of the flat for months together for one reason or the other.

After considering the arguments of the counsels representing both the parties the National Consumer Dispute Redressal Commission decided that the Complainant is required to be compensated for delay in construction of the flat and for not allotting the same to her. Because of the delay in construction and delay in deciding the matter, it is practically impossible for a retired Govt. employee to purchase a flat at the present price.

The National Consumer Dispute Redressal Commission further stated that therefore, there are two alternatives – (a) one is to give adequate compensation for delay and to direct the Opposite Parties to hand-over possession of an alternative flat in the vicinity of the area where the flat was allotted to the Complainant; (b) or secondly, to pay adequate compensation to enable the Complainant to purchase a new flat of the same area in the same or similar locality.

The Opposite Parties were directed to pay a sum of Rs.7,50,000/- as compensation to the Complainant for the period she suffered financially. This was on the presumption that the value of the flat has escalated. However, if the builder considers that compensation of Rs.7,50,000/- (Rupees seven lakhs and fifty thousand) is more or excessive, it would be open to the builder to provide an alternative flat of the size and price agreed, in the same locality or near about, to the complainant for which an appropriate allotment letter will be issued by them in favor of the Complainant within a period of eight weeks from the date of the order. If the same is not issued, it shall pay compensation of Rs.7,50,000/- to the complainant, as directed.

I repeat, the flat/premises buyers must insist to their builder for inclusion of penalty clause in their Agreement before execution of the same. The builder must deliver the project in time along with 100 per cent transparency in all the dealings. He must stick to the promised terms and conditions and pay penalty if the project delivery is late. Trust is the most important element in a society-builder relation and that should be well taken care of by the builder. Get all the promises or agreements made by builder in writing. It should outline the work to be done, date of completion, amenities or facilities promised.

I am an author of this article and an experienced Senior Counselor and Analyst for Redevelopment of Housing Societies since last many years with in-depth study of integral techniques with exclusively skilled in the various areas of Societies Laws and Redevelopment of Housing Societies.

 

There are several instances of incomplete or misleading information prevailing among the Housing Societies and flat owners as well that are planning for redevelopment. Controversial court judgments add to the confusion and such Housing Societies get stuck at some point due to lack of information, knowledge, contact with right kind of counselors, analysts, advisors etc. Many societies do not have conveyance and hence, the entire process can break down in an instant.

 

The Resident Members/Managing Committee Members of Housing Societies benefit my counseling and my full fledged Project management consultant to the fullest extent possible and gain valuable insights about the integral technicalities of various laws applicable to the redevelopment.

 

I hold direct interaction with the Resident Members/Managing Committee Members on the various parameters that are involved in Redevelopment of Housing Societies and solve most of their problems/provide adequate direction to represent their cases to various Authorities. At present, I have around 60 to 70 Housing Societies on my schedule who avail my services at a point of need.

 

I am well adept in Laws governing the Redevelopment of Housing Societies and distinctly experienced in studying and analyzing the entire text of Drafts of Development Agreement, Power of Attorney, Tender Document, Bank Guarantee and Individual Agreement to be executed with each member of the Society generally provided by the Developers/Builders to the Housing Society which are “Builder Friendly”. These drafts after thoroughly scanned and scrutinized by us and the gray areas are exposed and converted in to “Society Friendly” drafts.

 

I have published numerous articles on Internet for the benefit of Housing Societies in Mumbai. Please educate yourself and caution your friendly neighbors to be vigilant from Irregularities and illegalities in Redevelopment by the Builders, Illegal gratifications showered by Builders on corrupt members of Managing Committees, Rampant Corruption in BMC, Flagrant violation of Rules and Regulations by the Builders, how to beware of Cheat and Fraud Builders and their criminal and felonious acts.

  

  1. Planning for redevelopment? Read this……Guidelines on Redevelopment of

    Housing Projects in Mumbai

  2. Format of Indemnity Bond in Form M-20

  3. Letter of Consent for Redevelopment of Housing Societies

  4. Mismanagement by Managing Committees

  5. Section 101 of Maharashtra co-op. Societies act 1960 for recovery of dues 

      from defaulting members

  6. Unhealthy and Unlawful practice by certain Developers in Redevelopment of

      Housing Projects in Mumbai

  7. Importance of Indemnity Bond in Form M-20 for Managing Committees

  8. Code of Conducts for Developers: Redevelopment of Housing Societies and

      old Buildings in Mumbai

  9. Long Live Corruption in Redevelopment of Housing Societies in Mumbai

10. Guidelines for Selection of a good Builder

11. Busting of Redevelopment Projects of Housing Societies

12. Redevelopment of Housing Societies: Cessed Buildings in South Mumbai:

      Bonanza of FSI of 3.0 etc.

13. Code of Conduct for Builders Developers

14. Compensation to be paid by the Builder for delayed possession of flat

15. Corruption in Redevelopment

16. Redevelopment and corrupt Managing Committee Members

17. Redevelopment of Housing Societies and Sand Shortage

18. Redevelopment of Housing Societies: are Govt. Guidelines really persuasive

      and convincing?

19. Faults, Facts and Fundamentals about Redevelopment of Housing Societies

20. Redevelopment of Housing Societies.....what is Redevelopment that every

      Sociey wants to know?

21. Article series in Redevelopment of Housing Societies - Procedures for

      recording the minutes of various Meetings

22. Are your flats delivered in time?

 

Dilip Shah

Senior Counselor and Analyst for Redevelopment of Housing Societies

dilip7shah@gmail.com

9819825752, 32411533



Learning

 7 Replies

sachin singh (QA)     25 August 2011

Hi sir,

I am facing problem of late possesion atleast by 6 months. I booked the flat when only 6-7 months were remaining for possesion. So it is like 100% delay. What can i do for that i have already sent lot of mails to builder and they say kindly bear with us. I am paying rent (8500) and EMI. So six month delay will cause atleast 50000 rs loss.

Another Problem is that i feel area mentioned in floor plan of a room is less in reality. a corner is cut from the room. Will this be part of carpet area??

Thanks.

Sachin Singh

sachin.sqldeveloper@yahoo.co.in

9890842070

 

DILIP SHAH (Senior Counselor and Analyst for Redevelopment of Housing Societies)     26 August 2011

:PDear Mr. Sachin

You need to file a case against your Builder for compensation in

STATE CONSUMER DISPUTES REDRESSAL COMMISSION  at Administrative College, Room Nos. 1 and 2, Hazarimal Somani Marg, Opp. V.T. Station, Bombay - 400 001.

To file the case you need not have any Lawyer and the procedure is very simple. The judgment delivery is equally fast. You can plead your case on your own.

sachin singh (QA)     29 August 2011

Thanks for precious reply Sir.

I am from Pune. Will i need to go Mumbai again and again for my case ? Can i raise a complaint online? 

sachin singh (QA)     29 August 2011

If my builder has political connection then can he influence the decision of the court ? Can he create problems for me if i go in court for compensation ?

DILIP SHAH (Senior Counselor and Analyst for Redevelopment of Housing Societies)     30 August 2011

I am from Pune. Will i need to go Mumbai again and again for my case ? Can i raise a complaint online?

Reply: Yes. No online facility is available to file a case. 

If my builder has political connection then can he influence the decision of the court ? Can he create problems for me if i go in court for compensation ?

Reply: No.

sachin singh (QA)     05 September 2011

Hello Sir,

1. What is the right time to file a case? For example in my case according to agreement possession is in sep 11 but i was informed that i will get possesion in Mar 12(May be later). So i should file a case now or at the time of possesion ?

2. Please inform me if there is any branch of  court to file a case in pune regarding this. 

S. SRINIVASA RAO (Retired)     16 March 2012

The aggreived  has been advised to file a complaint in the Consumer Forum within two years.  It is not clear whether date specified for giving possession of the flat or the date on which the flat is given delivery will be counted for the two year period.  This may kindly be clarified.

2. If the builder indicates 1150 sq.ft for a 2BHK flat and he provides the carpet area of only 585 sq.ft treating the balance area as common area, corridors, lifts etc etc.  When the carpet area is just 585 sq.ft and when he is charging for the 1150 sq.ft, how far the builder's action is justified?  What should be the normal ratio / NORM between the carpet area and the common areas?

3. Whether areas covered by balconies constitute the carpet area?

Kindly enlighten on the above doubts.


Leave a reply

Your are not logged in . Please login to post replies

Click here to Login / Register