ANTICIPATORY BREACH OF CONTRACT
Rama Verma
(Querist) 10 April 2009
This query is : Resolved
PLEASE PROVIDE IN WHICH SECTION OF CONTRACT ACT ANTICIPOTORY BREACH OF CONTARCT CAN BE FOUND AND IS THERE ANY JUGDEMENT ON THIS ISSUSE.
Manish Singh
(Expert) 10 April 2009
Go through these cases
1. Jawaharlal Wadhwa And Another VS. Haripada Chakroberty 1989 SCC (1) 76
2. International Contractors Ltd. v. Prasanta Kumar Sur,[1961]3 SCR 579
Manish Singh
(Expert) 10 April 2009
Section 39 of the contract act.
Sachin Bhatia
(Expert) 02 October 2009
THE INDIAN CONTRACT ACT,1872
Sec 39.Effect of refusal of party to perform promise wholly.-When a
party to a contract has refused to perform, or disabled himself from
performing, his promise in its entirety, the promisee may put an end
to the contract, unless he has signified, by words or conduct, his
acquiescence in its continuance.