Interior manupulated and given very poor quality material
Than I Songs devisetti
(Querist) 13 October 2020
This query is : Resolved
Hi,
i have given contract to one interior( Imran ,Reflection imterior). He has given bill ,payment slips and paid through google pay but he had provided duplicate materials very low quality and what ever designs i have asked and he provided in diffrent way and he took more than 4 months as he supposed to complete in one month. still.he did not complete my project and what do and i really dont need these faulty products
Advocate Bhartesh goyal
(Expert) 13 October 2020
Supplying inferior or duplicate material and not completing the work within stipulated perIod comes under the purview of deficiency of services and unfair trade practice.File complaint against contractor before District Consumer Forum and claim cost of material and compensation.
P. Venu
(Expert) 13 October 2020
Before precipitating an action in a legal forum you have option to serve a Notice (preferably thorough a lawyer) detailing out the deficiencies in the material and the work, as executed seeking corrective action as well as damages.
kavksatyanarayana
(Expert) 13 October 2020
Agreed with the advice of learned experts.
Rajendra K Goyal
(Expert) 14 October 2020
Move to District Consumer Disputes Redressal Forum with a complaint of deficiency of service etc..