Tejas C 15 October 2017
Adv. Pradeep Bhatia 15 October 2017
Dear Tejas,
Yu can file a complaint in the RERA, however pl. 1st see what is the Allottment date given in your Agreement.
Also before filing the complant pl. check the reason the builders was unable to give the possession.
Regards,
Adv. Pradeep Bhatia
Tejas C 15 October 2017
Nitish Banka (lawyer) 24 April 2018
RERA is Real Estate Regulation Act-2016 the act was passed with an objective to regulate real estate sector in India. Real estate sector contributes to 9% GDP and is 2nd highest employment generator after Agriculture. There was a need to regulate the sector as there was huge number of builders who have defaulted in their commitment of giving possession of flat to allotees. The real estate scam in India is apparent and need to regulate builders was important an then there are one sided agreements and cheating done by builders
About 67% of projects in Delhi/NCR are delayed by more than 2 Years.
The act has a provision of mandatory registration of Builders and real estate agents and establishment of real estate regulatory authority to look into the matters related to complaint against builders.
A Builder complaint can be lodged in RERA under Section 31 of RERA Act.
Every State in India has RERA and under RERA builder projects are registered there are stringent provisions under which the builder has to disclose details of the project and file sanction plans,completion dates etc before he could even do marketing of the project. There are strict penalty clauses in the act with regards to non-registration of the projects.
Under Section 31 an allotee can approach RERA and can file builder complaint under RERA act. The format of complaint differ from state to state. Here we will evaluating RERA forums of Delhi and NCR.
Delhi Rera has interim Regulatory Authority situated at Vikas Minar ITO
Complete Address-:
14th Floor Vikas Minar, ITO, New Delhi
They have online complaint link https://dda.org.in/rera/EncroachDataUpload.aspx
However it is advisible to visit and file complaint under section 31 of RERA act against builders or rela estate agents in Delhi.
In Haryana two RERA authorities are there one in Panchkula and
Click here to download notification
The Gurgaon RERA is situated at make shift office PWD Guest house
Haryana Real Estate Regulatory Authority (H-Rera) will be finally set up in Gurugram from February 1, officials said.
The temporary office will start functioning out of the public works department (PWD) guest house on Old Railway Road near the Gurugram police commissionerate. However, the permanent office will come up in Sector 44 six months later.
UP Rera has a proper website and a link to lodge complaint
Website https://www.up-rera.in/index
Address
6 J.C.BOSE MARG, LALBAGH,LUCKNOW, Uttar Pradesh
E-mail: contactuprera@up-rera.in
The authority has wide powers for redressal of complaint under RERA hera are some of recent News of decisions by RERA
“The authority is of the view that Krisumi Corporation has violated the provisions by publishing the advertisement in the newspapers as well as on the website without getting prior registration of the project from the Haryana Real Estate Regulatory Authority, Gurugram in whose jurisdiction the said project falls and thereby committed the violation of Section 3 (1) of the Act and rendered themselves for action under Section 59 (1) of the ibid Act,” H-Rera chairman Khandelwal observed in the detailed order. Directing the company to pay Rs 30 lakh as penalty for the violations, the authority further observed that such violation would not be allowed.