Bhika Reghiwale   24 October 2020

My query

Our land acquired by National Highway for 60 mtrs road and paid compensation less due to the mistake in calculation of the area. They possessed it also as per layout map measurements.

After I came to know that the compensation paid is less.

Hence I lodged a complaint to Land Acquisition officer

He heared and found some land's compensation to be paid. It is calculated by Govt measurement. For it the second map is prepared and submitted by the measuring authority.

The main point is that the outer boundaries of my land acquired in both the maps are exactly the same, on which the land is acquired by completing all the formalities . The mistake is due to the  wrong calculations and internal placement of the land plot in the survey map along with other farmer's lands . Because it is a combined map of all these four farmers of one survey no.Therefore there is no any difference in disputed & acquired land ptlots.


Land  Acquisition Officer sent notice to Protect Director National Highway under 3 (1) of NH act.showing the quantity of land to be acquired.

Since then after 5 months of receipt of this notice P D does not send file back to LA till now .


Hence please advice 

A ) Is it necessary to repeat all the steps of NH act section 3 (A) in this case ? 


B) What should do the land acquisition Officer now ?


C) Can Land Acquisition officer

 hear any objection raised by N the P D NH ,  after a gap of 5 months vide 3 ( C ) (1) ?.


Learning

 2 Replies

G.L.N. Prasad (Retired employee.)     25 October 2020

First file RTI Application and seek information on action taken by Project director NH3 on your representation and present status.

Application dt.25th Oct,2020 seeking information under RTI Act

Before: CPIO, NH3..............

Fee: Postal order  No...Rs.10/-fvg.Accounts Officer, NH payable at New Delhi.

Applicant:.....................................

Subject on information sought:    Acquisition Officer  notice   Dt......to Projector  Director National Highway under 3 (1) of NH act.showing the quantity of land to be acquired-Land owner:............................at Survey No.........................................extent............................at.............................(Place) for the purpose of............................

 

Information solicited:

1.Please inform day to day action taken on AO notice till to date and provide such certified copies of all office notes for last 5 months.

2.Please inform present status
3.Please inform future course of action by NH3 for redressal of grievance by land owner.

 

Applicant.

Send the application with PO by Regd post, and paste the postal receipt on office copy of the application for further appeal process.   IF CPIO fails to respond within 35 days from posting of your application... file first Appeal to First Appellate authority, NH3.on deemed denial.
 

Dr J C Vashista (Advocate)     25 October 2020

It would be better to consult a local prudent lawyer for appreciation of facts / documents, professional advise and necessary proceeding.