Builder not completing remaining work
subhojit
(Querist) 06 August 2015
This query is : Resolved
Dear Sir - Hope to receive expert advise.I have purchased single aparment flat in 2013 & got possesion on July 2014.
Onwards then builder didn't complete the waterproffing & Lift, as he would be receving more FSI to increase one more floor, currently it is three floor apartment according to blue print. But till now no permission received & no progress in work.From the last year onwards my flat is damping as waterproffing not done. 2nd thing builder has closed the staircase above my floor made water tank above that & now if he construct flats in 4th floor there would be no option to go the terrace of 4th floor as stair case is closed.Does this is legal ? No open terrace in building.
How should we flat member act now, many verbal deadline builder has breached after making excuse that his extension permission is pending.Please advise.
P. Venu
(Expert) 07 August 2015
You can approach the consumer court.
subhojit
(Querist) 08 August 2015
Thanks Venu.Any addtional suggestion
subhojit
(Querist) 08 August 2015
Please advise as society is also not formed out of 12 Flat members only we 7 are reachable.how to file consumer complaint & what would be the impact
subhojit
(Querist) 08 August 2015
Please advise as society is also not formed out of 12 Flat members only we 7 are reachable.how to file consumer complaint & what would be the impact
subhojit
(Querist) 10 August 2015
I am from Pune