E STAY ORDER ON FUEL SURCHARGE ADJUSTMENT (FSA) NOTIFICATION BY AP HIGH COURT-
IN THE HIGH COURT OF JUDICATURE OF ANDHRA PRADESH
AT HYDERABAD
TUESDAY THE TWENTY SEVENTH DAY OF JULY
TWO THOUSAND AND TEN
: PRESENT:
THE HON'BLE SRI JUSTICE SANJAY KUMAR
WPMP.NO: 23008 of 2010
IN
WP.NO: 18214 of 2010
Between:
-
M/s. Arabindo Pharma Ltd., Plot NO. 2, Mythri Vihar, Ameerpet, Hyderabad-500038, rep. by its General Manager (Legal) and Company Secretary, Shir A. Mohan Rami Reddy.
-
K.J. Venkata Rama Reddy, S/o. K.J. Virupaksha Reddy.
...Petitioners
(Petitioner in WP 18214 of 2010
on the file of High Court)
AND
1 Andhra Pradesh Electricity Regulatory Commission, Singareni Bhavan, Red Hills, Hyderabad, rep. by its Chairman.
2 Andhra Pradesh Power Coordination Committee, Vidyuth Soudha, Hyderabad, rep. by its Chief Engineer (Commercial)
3 Central Power Distribution Company of Andhra Pradesh, Ltd., Mint Compound, Secretariat Road, Hyderabad, rep. By its Managing Director.
4 Eastern Power Distribution Company of Andhra Pradesh Ltd., rep. by its Managing Director, Sai Shakti, Opp: Sarswati Park, Daba Gardens, Visakhapatnam-530020.
5 The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Sangareddy, Medak District.
6 The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Mahabubnagar, Mahaboobnagar District.
7 The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Srikakulam Srikakulam District.
8 The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Gunrock, Secunderabad, Ranga Reddy District.
9 The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Sangareddy, Medak District.
10 The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Mahabubnagar, Mahabubnagar District.
11 The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Srikakulam, Srikakulam District.
12 The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Gunrock, Secunderabad, Ranga Reddy District.
...Respondents
(Respondents in-do-)
COUNSEL FOR PETITIONER : Sri Ch. Gunaranjan
COUNSEL FOR RESPONDENT No. 1 : Sri P.Sri Raghuram
COUNSEL FOR RESPONDENT No. 2, 3 and 5 to 12 : Sri O. Manohar Reddy
COUNSEL FOR RESPONDENT No. 4 : Smt. G. Jyothi Eswhar
Petition under Section 151 of C.P.C., praying that in the circumstances stated in the affidavit filed in the Writ Petition the High Court may be pleased to suspend the operation of the orders issued by the 1st respondent in proceeding Nos. APERC/Secy./Jt.Dir.(Traff-Engg.)/No.05, APERC/Secy./Jt.Dir.(Traff-Engg.)/No.06, APERC/Secy./Jt.Dir.(Traff-Engg.)/No.07, APERC/Secy./Jt.Dir.(Traff-Engg.)/No.08, dated: 05-06-2010, pending disposal of the W.P. No. 18214 of 2010 on the file of the High Court;
..2..
The court while directing issue of notice to the Respondents herein to show cause as to why this application should not be complied with, made the following order.(The receipt of this order will be deemed to be the receipt of notice in the case).
ORDER:
“Interim suspension, as prayed for”.
ASSISTANT REGISTRAR
//TRUE COPY//
For ASSISTANT REGISTRAR
To
-
The Chairman, Andhra Pradesh Electricity Regulatory Commission, Singareni Bhavan, Red Hills, Hyderabad.
-
The Chief Engineer (Commercial), Andhra Pradesh Power Coordination Committee, Vidyuth Soudha, Hyderabad.
-
The Managing Director, Central Power Distribution Company of Andhra Pradesh, Ltd., Mint Compound, Secretariat Road, Hyderabad.
-
The Managing Director, Eastern Power Distribution Company of Andhra Pradesh Ltd., Sai Shakti, Opp: Sarswati Park, Daba Gardens, Visakhapatnam-530020.
-
The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Sangareddy, Medak District.
-
The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Mahabubnagar, Mahaboobnagar District.
-
The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Srikakulam Srikakulam District.
-
The Superintendent Engineer, Operation Circle, Central Power Distribution Company of Andhra Pradesh Ltd., Gunrock, Secunderabad, Ranga Reddy District.
-
The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Sangareddy, Medak District.
-
The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Mahabubnagar, Mahabubnagar District.
-
The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Srikakulam, Srikakulam District.
-
The Senior Accounts Officer, Operation Circle, Central Power Distribution Company of Andhra Pradesh, Ltd., Gunrock, Secunderabad, Ranga Reddy District. (ADDRESSEES 1 TO 12 BY RPAD)
-
One CC to Sri Ch. Gunaranjan, Advocate (OPUC)
-
Two spare copies.
Ksv
HIGH COURT
Ksv
Date of drafting: 28-07-2010
SKJ
DATE: 27-07-2010
ORDER
WPMP NO. 23008 OF 2010
IN
WP. NO. 18214 OF 2010
INTERIM SUSPENSION