Any delay charges for builder in delay in handing over of commercial property
swami
(Querist) 01 February 2013
This query is : Resolved
1. BOOKED A SHOP IN A MALL IN 2005.
2. PAID 60% OF AMOUNT BY2006.
3. BUILDER WAS SUPPOSE TO HAND OVER THE SHOP IN 2007.
4. HANDING OVER IN JAN 2013.
5.REQUST ADVISE.
ajay sethi
(Expert) 01 February 2013
read agreement signed with builder . does contract prvoide for payment of innterest for delayed posession . is he paying interest
R.K Nanda
(Expert) 01 February 2013
u can claim damages for delay.
V R SHROFF
(Expert) 01 February 2013
If delay due to negligence , and contract/Agreement shows a date of possession, Consumer forum will direct builder to compensate you for delay.
Raj Kumar Makkad
(Expert) 02 February 2013
You are entitled to file consumer complaint and claim interest thereon.
ajay sethi
(Expert) 02 February 2013
since querist has failed to reply to clarifications sought it appears he is no longer interested in redressal of his grievance