Breaking an agreement

(Querist) 19 February 2017 This query is : Resolved 
I have given my house construction work to a contractor.
In the stamp paper it is mentioned that he has to finish all mentioned work in the limited time. 16th February 2017 was the last date. I have remind him many time about the time bound in agreement, but he take it lightly.
Only boundary wall, main gate is left and he started skipping my work . I guess at the ongoing speed he will finish till 15 march.

My question is can I deduct some amount as a fine from the last amount which I have to pay him at the end of work?

* Nothing is mentioned in agreement about fine/punishment for not finishing work in given time limit.
Adv. Yogen Kakade (Expert) 20 February 2017
Stop the balance payment and send him a legal notice mentioning the amount of fine.
Rajendra K Goyal (Expert) 20 February 2017
REMIND HIM IN WRITING.

Send legal notice.

Proceed as per terms of agreement if signed by both parties.
Ms.Usha Kapoor (Expert) 21 February 2017
Agree with experts.