Delay in construction of project
RAJESH CHOPRA
(Querist) 10 April 2016
This query is : Resolved
Sir , I had booked an office space in prelaunch in a mixed land use project in Noida in Nov 2012. The agreement with builder was done in June 2013 and as usual it was more in favor of builder with 35% cancellation charge and with meagre penalty on account of delay.
The construction of project is moving at very slow pace and builder has in between changed the layout also. i had paid 50% of the value.
Now I need money for my personal use and the purpose for which the office space was booked is not served.
What is the remedy for me. which legal forum to approach in individual capacity. Shud I do some written correspondence with builder before moving to court. How will RERA help me.
Advocate Kappil Cchandna
(Expert) 10 April 2016
Sir,
Simply file the case before the consumer forum for defective services and take your money back from them, no need to send them any notice or anything ...
Warm Regards
Kapil Chandna Advocate
9899011450
R.K Nanda
(Expert) 10 April 2016
take acknowledgement, in writing from builder about ur payment to them, of recent date so as to bring case in limitation period which otherwise is time barred as per CPAct.
Rajendra K Goyal
(Expert) 10 April 2016
You may not get immediate relief for your needs from the builder side.
File consumer complaint.
Advocate Bhartesh goyal
(Expert) 10 April 2016
You have to file complaint against builder before Consumer Forum on ground of his deficiency in services and have to claim the. money which was paid to builder along with compensation for mental and physical agony caused to you.