Factory License
Himanshu
(Querist) 01 December 2009
This query is : Resolved
We have applied for transfer of factory licence in our name for factory situated in Maharashtra, West Bengal and Delhi. But even after follow-up with the authority for 8 to 10 months and submission of all required documents thay are not transfering license in our name. Is thare any provision under Factories Act that if they do not transfer within specified time from the date of our application then it will be considered as deemed approval for transfer. Please advise.
Raj Kumar Makkad
(Expert) 01 December 2009
No. There is no such provision in Factories Act but you move an application under RTI Act seeking the valid period, day to day action on your application and present status so that it may be moved fast.