I am (M P RAJESWAR) residing in Flat No G4, SNB Apartments,Parameswari Nagar,Nellore Andhrapradesh.
The Builder of our apartment was not completed the apartment the way it has to be.1.Not provided completion and occupancy certificate.2.Allowed more than 2 promoters.
No rules were followed like deviation on the approved plan.
these reasons have given entry to others to take undue advantage over this.
like cellar occupation with constructions of flats.Parking area is offered for sale.
In this process here in our apartment some opportunists joined hands with the promoters(Who went out) formed as association here and plan to take advantage of the situation like miss using public fund,not paying house tax and miss using the power taking a proxy (not owning a flat in the apartment) as a treasurer in the committee who ever question them about the above Harass/Humiliate or trouble them a lot.
suggest me how to protect me from these trouble shooters and what is the punishment for these type of people how to proceed with this issue.
M P RAJESWAR
7396317071
Adv. Yogen Kakade
(Expert) 21 December 2015
What are the terms decided in the agreement about the duration to complete the construction and give possession? The other promoters or persons are none of your concern.. the person who has promised you and agreed terms in agreement is liable for the commitments.. consult a local lawyer and send legal notice.
Rajendra K Goyal
(Expert) 21 December 2015
If the builder has not fulfilled agreed terms move to consumer forum. You have to take stand in case of outsiders and take legal steps against them as and when warranted.
K.S.Srinivas
(Expert) 26 December 2015
File a complaint in the District Consumer Forum against the Builder for violation of Terms & Conditions of the agreement.